Injection Enhancement Phase 2 Feasibility Study*

Centrica Storage.png

Client: Centrica Storage Limited

Field (Type): Rough (Gas Storage; Offshore & Onshore UK)

Project Name: Injection Enhancement Phase 2 Feasibility Study

Value Added: Appraisal of enhancement options; 23% increase in injection rates feasible; implementation road map


PROJECT DESCRIPTION:

  • Duration: approx 3 months

  • Role: Project/Study Management & Engineering (Engineering Consultant)

  • Disciplines involved: Rotating Equipment Engineering, Process Engineering and Project/Study Management

  • Project interfaces: Direct with end client

DELIVERABLES:

  • Following previous successful injection enhancement project, explore feasibility for further injection enhancements via minor and major operational and equipment modifications

  • Simulate and validate existing baseline injection deliverability of the asset

  • Identify potential injection debottlenecking opportunities

  • Prepare and recommend phased implementation road map